With the significantly lower footfall (and therefore hopefully risk), the extended summer break is an opportune time for education providers to schedule construction and/or refurbishment projects. In doing so, many UK-based academies, sixth-form colleges and voluntary aided schools may be benefitting from receiving a share of the government’s £456m Condition Improvement Fund refurbish and repair dilapidated school buildings this year.
Although 6 – 8 weeks seems a vast amount of time to parents and pupils, it is a relatively modest period for construction works, depending on the scale of the project. The usual worry for education providers and contractors working on projects on site at schools or campuses etc., is that the works overrun into term time when pupils and staff are back. This could result in the education provider needing to use the newly, or partly built accommodation before completion, and of course there are many health and safety issues too.
Sometimes, the reason for the overrun is outside the contractor’s control – it is not unusual to have heavy thunderstorms and flash flooding in August. The ongoing shortages with materials and labour also continue to affect the construction sector and can have an impact on tight timetables.
So what can you do to help mitigate the risk of a project overrunning?
Be clear with the contractor about your deadlines from the outset and have regular, frank and open commercial discussions about progress and how realistic your proposed programme for the works really is. Such discussions are in the interests of all parties and can prove to be one of the most effective methods of ensuring the project meets its targets.
Some examples of discussions we have seen that benefit projects include:
Most importantly, remember that trust is key.
In circumstances like this where time is very much of the essence, it is critical that all parties have a clear understanding of what the contractual terms are, the strength of their bargaining position and their legal standpoint at the inception of the project and long before the works even commence – seeking legal advice is an invaluable step in that process. Often once a contract has been signed there is very little room for re-negotiations and generally relies on good will. Therefore, it is imperative to get things right before execution stage and below are just a few examples of how this can be achieved:
Last year, our Construction team advised a leading private school based in Cambridgeshire on two new projects including the refurbishment of buildings in the campus and the other a new build primary school. We also advised a Cambridge College on a major recreational facilities project for students which recently achieved practical completion having started during 2020 amongst all the problems of lockdown and restrictions on construction. We drafted the consultant appointments with the building contract and other construction documents for all these projects and more general construction advice throughout.
If you need help with a construction project whether at inception stage, tendering or later, please get in touch.
This update is for general purposes and guidance only and does not constitute legal or professional advice. You should seek legal advice before relying on its content. Greenwoods Legal LLP is a Limited Liability Partnership, registered in England, registered number OC306912. Our registered office is Queens House, 55-56 Lincoln’s Inn Fields, London, WC2A 3LJ. A list of the members’ names is available for inspection at our offices in Peterborough, Cambridge and London. Authorised and regulated by the Solicitors Regulation Authority, SRA number 401162. Details of the Solicitors’ Codes of Conduct can be found at www.sra.org.uk. All instructions accepted by Greenwoods Legal LLP are subject to our current Terms of Business. VAT Reg No: 161 9287 89.